CRF: Parking Facilities

Parking fund · Parking Fund · 20-year horizon

Every figure the reserves table quotes for this fund, derived again here line by line. The bar in a public meeting is not trust-the-software; it is check line four.

← all reserve funds · horizon 6 years10 years20 years

The answer

At today's deposit of $84,000 this fund covers every draw on the horizon. Nothing more is required.

One recurrence, applied 20 times: balance = balance × (1 + 0.0%) + deposit − draws. Deposits are today’s figure, held flat. No solver and no goal-seek — the answers below are closed-form, so the same inputs always give the same figures.

Balance, both ways

negatives are shown, never floored — a fund going under is the finding
$0$198k$396k$594k$792kAt today’s deposit · FY2028 · $360,574At today’s deposit · FY2029 · $134,074At today’s deposit · FY2030 · $116,174At today’s deposit · FY2031 · $158,174At today’s deposit · FY2032 · $209,174At today’s deposit · FY2033 · $215,524At today’s deposit · FY2034 · $161,524At today’s deposit · FY2035 · $215,524At today’s deposit · FY2036 · $279,524At today’s deposit · FY2037 · $363,524At today’s deposit · FY2038 · $422,524At today’s deposit · FY2039 · $506,524At today’s deposit · FY2040 · $590,524At today’s deposit · FY2041 · $674,524At today’s deposit · FY2042 · $707,524At today’s deposit · FY2043 · $791,524At today’s deposit · FY2044 · $435,524At today’s deposit · FY2045 · $519,524At today’s deposit · FY2046 · $603,524At today’s deposit · FY2047 · $687,524With the gradual step-up · FY2028 · $360,574With the gradual step-up · FY2029 · $134,074With the gradual step-up · FY2030 · $116,174With the gradual step-up · FY2031 · $158,174With the gradual step-up · FY2032 · $209,174With the gradual step-up · FY2033 · $215,524With the gradual step-up · FY2034 · $161,524With the gradual step-up · FY2035 · $215,524With the gradual step-up · FY2036 · $279,524With the gradual step-up · FY2037 · $363,524With the gradual step-up · FY2038 · $422,524With the gradual step-up · FY2039 · $506,524With the gradual step-up · FY2040 · $590,524With the gradual step-up · FY2041 · $674,524With the gradual step-up · FY2042 · $707,524With the gradual step-up · FY2043 · $791,524With the gradual step-up · FY2044 · $435,524With the gradual step-up · FY2045 · $519,524With the gradual step-up · FY2046 · $603,524With the gradual step-up · FY2047 · $687,524FY28FY29FY30FY31FY32FY33FY34FY35FY36FY37FY38FY39FY40FY41FY42FY43FY44FY45FY46FY47
At today’s depositWith the gradual step-up

The roll-forward, line by line

every draw names its projects
YearDepositDrawsDrawn byBalanceStep-up depositBalance, stepped
Openingavailable, net of commitments, as of 31 Oct 2025$301,874$301,874
FY2028$84,000$25,300EV Charging Stations lower deck $25,300$360,574$84,000$360,574
FY2029$84,000$310,500Pay & Display Meter Stations (21) $157,500Control Access Equipment $125,000Sealing exposed bricks $28,000$134,074$84,000$134,074
FY2030$84,000$101,900Security Cameras Pkg 7 Leb $50,700Expansion Joint and Capstones $34,200Lot 5 West Wheelock $17,000$116,174$84,000$116,174
FY2031$84,000$42,000Lot 1 Paving $42,000$158,174$84,000$158,174
FY2032$84,000$33,000Lebanon St Lot 7 parking $33,000$209,174$84,000$209,174
FY2033$84,000$77,650911 Call Boxes/cell mesh network $38,650Garage joint/membrane repair $20,000CCTV Cameras Parking Garage & Lot 1 $19,000$215,524$84,000$215,524
FY2034 ·beyond the window$84,000$138,000Lighting upgrades $80,000Hopkin Center Parking $58,000$161,524$84,000$161,524
FY2035 ·beyond the window$84,000$30,000Pay & Display Meter Station (4) $30,000$215,524$84,000$215,524
FY2036 ·beyond the window$84,000$20,000Allen Lot Paving $20,000$279,524$84,000$279,524
FY2037 ·beyond the window$84,000$363,524$84,000$363,524
FY2038 ·beyond the window$84,000$25,000Banwell Lot $25,000$422,524$84,000$422,524
FY2039 ·beyond the window$84,000$506,524$84,000$506,524
FY2040 ·beyond the window$84,000$590,524$84,000$590,524
FY2041 ·beyond the window$84,000$674,524$84,000$674,524
FY2042 ·beyond the window$84,000$51,000Lot 1 Lighting $51,000$707,524$84,000$707,524
FY2043 ·beyond the window$84,000$791,524$84,000$791,524
FY2044 ·beyond the window$84,000$440,000Structural, membrane, Cosmetic & repairs $440,000$435,524$84,000$435,524
FY2045 ·beyond the window$84,000$519,524$84,000$519,524
FY2046 ·beyond the window$84,000$603,524$84,000$603,524
FY2047 ·beyond the window$84,000$687,524$84,000$687,524

What is lingering just outside the window

this is what drives the contribution
YearAssetDraw
FY2034Lighting upgrades$80,000
FY2034Hopkin Center Parking$58,000
FY2035Pay & Display Meter Station (4)$30,000
FY2036Allen Lot Paving$20,000
FY2038Banwell Lot$25,000
FY2042Lot 1 Lighting$51,000
FY2044Structural, membrane, Cosmetic & repairs$440,000
A fund can look over-funded inside a six-year window and be correctly funded once the assets landing beyond it are on screen. The recommended contribution is computed on the full horizon, which is why this panel exists.