Window FY2028–FY2033Scenario

Treatment Modules MMM1, compressor & VRD

WATER-010
WaterWaterWater Treatment FacilityWaterIn the planclassification proposed

Cost by year

$172,000 total
YearExpenditure typeBasisAmount
FY2033not statedno basis$172,000

Funding by source and year

more than one source per year is supported
SourceClassFY33Total
CRF: Water TreatmentSaved in advance$172,000$172,000
Residual against cost0$0

Actual spend

manual entry or CSV

Nothing recorded. Actuals sit at the same grain as the funding above — by year and by source — so plan against actual works at the level the money was planned at.

Life cycle

Useful life10 yrs
Condition
Last purchase2023-07-01 00:00:00
Previous investment$116,000
Next investment$172,000
Trade-in value
Replacement yearFY2033

The Town paid $116,000 last time and will pay $172,000 next — 48% more.

Classification

proposed
Importance2
Timing rationaleCondition
Project typeReplacement or maintenance

Proposed by rule. Nobody has confirmed it, so nothing built on these values states a fact.

Movement window

Not set. How far this project can move does not exist in the register, and the scenario engine cannot move anything without it. This is a question for the department, not a default.

Narrative

There are a total of 140 filtration modules that have a 15 year life, 40 modules will be replaced during this phase. The modules provide ultrafiltration of bacteria and solids down to 0.1 microns. Providing 99.999% removal of bacteria.

A picture is recorded in the register at S:\databases\CIP database\photos\Water\filter modules.jpg — upload it on the edit page to show it here.

Who pays

CRF: Water Treatment — Water user fees, Water Fund.