Window FY2028–FY2033Scenario

Hydro Seeder

R-CIP-0148
Public WorksGroundsRolling StockGeneralIn the planclassification derived

Cost by year

$14,000 total
YearExpenditure typeBasisAmount
FY2043not statedno basis$14,000

Funding by source and year

more than one source per year is supported
SourceClassFY43Total
CRF: Highway EquipmentSaved in advance$14,000$14,000
Residual against cost0$0

Actual spend

manual entry or CSV

Nothing recorded. Actuals sit at the same grain as the funding above — by year and by source — so plan against actual works at the level the money was planned at.

Life cycle

Useful life25 yrs
Condition
Last purchase2018-07-07 00:00:00
Previous investment$7,800
Next investment$14,000
Trade-in value$2,811
Replacement yearFY2043

The Town paid $7,800 last time and will pay $14,000 next — 79% more.

Classification

derived
Importance
Timing rationale
Project type

Proposed by rule. Nobody has confirmed it, so nothing built on these values states a fact.

Movement window

Not set. How far this project can move does not exist in the register, and the scenario engine cannot move anything without it. This is a question for the department, not a default.

Narrative

This piece of equipment is used to seed disturbed areas and reseed playing fields.

A picture is recorded in the register at S:\databases\CIP database\photos\Vehicles\hydroseeder.jpg — upload it on the edit page to show it here.

Who pays

CRF: Highway Equipment — Property taxes, General Fund.